                            Implementation of  software for doing business - module IM/PS (IM/PS) for investments 
In  2014 for the implementation of the module IM/PS (IM/PS) the following  activities were realized: 
                            
                              
                                - Defining the workflow for  approving investments, 
- Training for Key Users and  End Users, 
- Investment programs for all  subsidiaries and the Direction were manually entered in the SAP system , 
- 20 capital and 250 small  projects through investment requirements were manually entered, 
- Carried out preparatory  activities for the module IM/PS (IM/PS) for Golive 2015 with the preparation of  data should remain in the system. 
 
                            Implementation of the  system for environmental protection ISO 14001 for the needs of JSC ELEM 
                            
                              - Finished first internal audit in all branches of JSC  ELEM in May 2014. 
- Finished external audit in June 2014. 
- Second internal audit in the all subsidiaries of JSC  ELEM (excluding the Direction) in December 2014. 
- Activities have been launched to implement the process  for recertification of ISO 14001on the   level of JSC ELEM. 
Annual investment  activities 
                            
                              - A report on the  implementation of investment activities in 2013 was prepared and submitted for  approval to the MB. 
- A report on the annual  investment in fixed assets for 2013 was prepared for the State Statistical  Office - Skopje. 
- Made Reports on realization  of investment activities for the period 1-6. 2014 and for the period 1-9. 2014. 
- Following the  implementation of the annual investment program for 2014 of JSC ELEM for all  production subsidiaries and departments in the Direction. 
- Processed and approved  monthly plans with requests for starting investment activities and relocation  of funds (by decisions of the MB), and approval of technical specifications. 
- A draft annual investment  program for 2015 was prepared and adopted the MB. 
- Delivered data on plan and  realization of the investment program to the Regulatory Commission. 
- Delivered  quarterly reports on realization of investments for 2014 to SSO. 
- Construction  of a new administrative facility- "Office building ELEM" on the  street.  Makedonija bb in Skopje
- Participation in the  Commission for technical support to the project under construction. 
 
                            Reconstruction and  construction of the facade of the administrative building of EVN Makedonija and  JSC ELEM 
                            
                              - Participation in the  Commission for technical support to the project under construction. 
Other activities 
                            
                              - Participation in the  Commission for conducting an internal technical review of boiler in subsidiary  Energetika. 
- Participation in the  working group for the implementation of capital projects and modernization of  facilities of ELEM TOURS: 
- Pedestrian-bicycle paths on  Lake Kozjak near the settlement Blizansko, 
- Pools of water to produce  artificial snow for ski centre Kopanki, Bitola, 
- Geotechnical investigations  for hotel "Molika" Pelister and hotel "Slavija" Popova  Shapka, 
- Participation in the  working group to present a proposal for rehabilitation of the completed  excavation for water tank on Popova Shapka, 
- Participation in the  technical evaluation of bids for: construction of an outdoor handball playground in Struga. 
- Participation in the  technical evaluation of bids for: engaging monitoring authority complete inspection and oversight over: 
- Organization and  realization of the works: Construction of parking for  public use and a drainage channel of the ski centre Popova Shapka, 
- Organization and  implementation of works on construction of outdoor handball playground in  Struga. 
- Participation in the  technical evaluation of bids for: engaging a supervisor to conduct a full inspection and supervision of  the organization and conduct of works during the construction of six seat  chairlift at ski resort Popova Shapka. 
- Participation in the  technical evaluation of bids for: Preparation of project-technical documentation for construction of the  ski centre Vodno.